Service resumed on Kitsap Fast Ferry on Friday afternoon after morning cancellations for mechanical issues. It was the 12th time that service has been disrupted, and Kitsap Transit said there could be damage to some engine components after the boat sat in storage for five years.

The Kitsap Fast Ferry was back in service Friday afternoon after missing morning sailings due to mechanical problems, but Kitsap Transit said there could be issues with the boat’s engine components after it sat in storage for five years.

Friday morning was the 12th time since the ferry’s July 10 launch that service was disrupted for repairs or mechanical issues.

Sailings were also canceled Thursday afternoon.

The ferry runs three morning and three afternoon round trips between Seattle and Bremerton. The trip, for foot and bike passengers only, takes about half the time as Washington State Ferries’ standard route, but also costs about 50 percent more.

Most Read Stories

Unlimited Digital Access. $1 for 4 weeks.

Fast-ferry service returned to the route in July, after a decade’s absence. Previous state-run fast ferries shut down in 2003, after property owners on Rich Passage — the narrow strait between Bainbridge Island and Kitsap Peninsula — sued, claiming the fast ferry’s larger wakes were damaging their beaches.

The new ferry solved that problem with a hydrofoil, essentially an underwater wing that lets it ride higher in the water and leave a smaller wake. But there have been mechanical issues in the early going.

On Friday, a recently installed strainer, which filters seawater used to cool the engine, broke, sending water into another compartment and short-circuiting part of the ferry’s jet-propulsion system.

The ferry, the Rich Passage 1, had problems with its propulsion-control system in July, the Kitsap Sun reported. Other cancellations were caused by a failed turbocharger and a blown head gasket.

In September, sailings have been canceled on six days in total because of damage to the boat’s hull, an exhaust-system problem and the broken strainer.

Kitsap Transit has owned the boat since 2012, when it ran for several months to test its wake. But it has had little use since then.

“It appears some engine components degraded over the five years the boat was in storage,” Kitsap Transit spokesman Sanjay Bhatt said. “We also now know the exhaust system’s design contributed to high pressures on the engines. We are…